| Cardinal Healthcare
San Diego, California

Michael Wall Engineering, Inc. prepared electrical construction documents for a tenant improvement of approximately 554,000SF designed in two phases: Phase one consisted of approximately 180,000SF of office/manufacturing space; phase two consisted of approximately 374,000SF of office space within two buildings. The first phase contains a 40,000SF manufacturing lab that features ceiling-mounted utility panels. Each panel contains power, data, vacuum, compressed air, and reference ground. The 25,000SF call center uses under-slab equipment to allow easy reconfiguration of furniture systems. All lighting systems feature high output T5 lamps for maximum efficiency.
Specialized Engineering:
554,000SF Campus
40,000SF Manufacturing Lab
5,000SF Research Lab
300SF Data Center
(Two) 4000A 480Y/277V Services
800kW Emergency Generator
2MW Standby Power System
Architect:
Pacific Cornerstone Arechitects
Return to Projects
|